Welker® Probe-Mounted Liquid Eliminator with Liquid Shut-off Installation, Operation, Maintenance Manual
Industry Manual Repository
Join the AnalyzeDetectNetwork and Read This Manual and Hundreds of Others Like It! It's Free!
Installation, Operation, and
Maintenance Manual
Welker® Probe-Mounted Liquid Eliminator
with Liquid Shut-off
Model
LE-2SSKO with ALS
Drawing No.: AD126EF
Manual No.: IOM-164
The information in this manual has been carefully checked for accuracy and is intended to be used as a guide for the
installation, operation, and maintenance of the Welker® equipment described above. Correct operating and/or installation
techniques, however, are the responsibility of the end user. Welker ® reserves the right to make changes to this and all
products in order to improve performance and reliability.
This manual is intended to be used as a basic installation and operation guide for the Welker® ProbeMounted Liquid Eliminator with Liquid Shut-off, LE-2SSKO with ALS. For comprehensive
instructions, please refer to the IOM Manuals for each individual component. A list of relevant
component IOM Manuals is given in the Appendix section of this manual.
13839 West Bellfort
Sugar Land, TX 77498-1671
(281) 491-2331 - Office
(800) 776-7267 - USA Only
(281) 491-8344 - Fax
http://www.welkereng.com
©2013 Welker, Inc. All Rights Reserved.
TABLE OF CONTENTS
Welker®, Welker Jet®, and WelkerScope® are Registered Trademarks owned by Welker, Inc.
IOM-164
PART #: LE2SSKO-MI with ALS
Rev: -
Last Updated: 1/15/2013
Page 2 of 11
Section 1:
SPECIFICATIONS
We appreciate your business and your choice of Welker® products. The installation, operation, and
maintenance liability for this product becomes that of the purchaser at the time of receipt. Reading
the applicable Installation, Operation, and Maintenance (IOM) Manual prior to installation and
operation of this equipment is required for a full understanding of its application and performance
prior to use.*
If you have any questions, please call 1-800-776-7267 (USA) or 1-281-491-2331.
*The following procedures have been written for use with standard Welker ® parts and equipment. Assemblies that
have been modified may have additional requirements and specifications that are not listed in this manual.
The Welker® Probe-Mounted Liquid Eliminator with Liquid Shut-off is designed to condition gas
samples for an analyzer. This product combines an adjustable, manual insertion sample probe; an
LE-2SSKO style liquid eliminator with isolation valves; and an analyzer liquid shutoff (ALS). The
liquid eliminator is designed to collect a sample of gas from the pipeline while returning any liquids
to the pipeline. To protect the analyzer from potential liquid damage, the ALS allows gases to pass
through but will shut off if any liquid passes the liquid eliminator and enters the ALS.
The specifications listed in this section are generalized for this equipment. Welker® can
modify the equipment according to your company’s needs. However, please note that the
specifications may vary depending on the customization of your product.
Table 1: System Specifications
Products Sampled
Gas
Materials of Construction
316/316L Stainless Steel, Carbon Steel, Teflon®, Kalrez®, Glass (ALS)
Maximum Allowable Operating Pressure
285 psi @ -20o to 100oF
(20 bar @ -29o to 38oC)
Maximum Allowable Operating Temperature
Maximum Allowable Insertion Pressure
130oF @ 277 psig (55oC @ 19 bar)
For Manual Insertion: 110 psig (7.6 bar)
Probe Connection
IOM-164
PART #: LE2SSKO-MI with ALS
Rev: -
1”-150 RF Standard
Others available upon request.
Last Updated: 1/15/2013
Page 3 of 11
Figure 1: System Diagram
Figure 2: Recommended General Arrangement
IOM-164
PART #: LE2SSKO-MI with ALS
Rev: -
Last Updated: 1/15/2013
Page 4 of 11
Section 2:
INSTALLATION & OPERATIONS
After unpacking the unit, check the equipment for compliance and for any damage that may
have occurred during shipment. Claims for damage caused during shipping must be
®
initiated by the receiver and directed to the shipping carrier. Welker is not responsible
for any damage caused by mishandling by the shipping company.
When sealing fittings with PTFE tape, refer to the proper sealing instructions for the tape
used.
1. Welker® recommends that the probe be installed in such a way as to extract the sample from the
center one-third (1/3) of the pipeline or wherever the collected sample will be representative of
the product as a whole.
2. The probe should be installed upright in the top of the pipeline.
3. The preferred location for installation is in a straight section of inlet piping upstream of any point
at which the flowing stream is subjected to turns and impingements. Any such impingement may
result in aerosols that may produce a sample that is not representative of the gas in the pipeline.
4. The probe should be located in the least turbulent area of the flowing stream available (i.e., not in
a header or blow-down stack and away from obstructions, elbows, or partially closed valves).
Positioning the stop collar (Figure 3):
1. Before installing the probe, the length the insertion probe will need to travel inside the pipeline
must be determined. Measure the distance the probe must travel from the top of the pipeline
isolation valve to the desired insertion depth (e.g., center 1/3 of the pipeline). This will be the
probe insertion length.
2. Ensure that the probe is fully retracted. The probe tip should be flush with the bottom of the
adapter.
3. Beginning at the top of the body, measure up on the probe from the bottom of the probe tip to the
desired insertion length. It may help to mark this point with a felt-tip pen.
4. Loosen the two set screws in the stop collar, and move the bottom of the stop collar to the
desired probe insertion length, or the mark made in Step 3.
5. Tighten the set screws in the stop collar to hold the stop collar in place on the shaft.
Figure 3: Positioning the Lock Collar
IOM-164
PART #: LE2SSKO-MI with ALS
Rev: -
Last Updated: 1/15/2013
Page 5 of 11
Installing the Probe:
1. Ensure that all valves are closed.
2. With the pipeline isolation valve closed and the probe shaft fully retracted, bolt the probe onto
the pipeline flanged connection at the desired location. Install the probe in a manner consistent
with the recommendations given in Section 2.1.
3. Depressurize the pipeline to approximately 100 psi for safe manual insertion.
Ensure the pipeline is depressurized to below 110 psig for safe manual installation.
Inserting the probe at a pipeline pressure greater than 110 psig may result in injury to the
operator or damage to the equipment.
4. Slowly open the pipeline isolation valve.
5. Firmly push the shaft into the pipeline.
When pushing the shaft into the pipeline, push straight downward; do not allow the shaft to
bend. Do NOT insert the probe at pressures higher than the pressure specified in Table 1 of
these instructions.
6. Tighten the stop collar spacer bolts to lock the stop collar in place. Continue to push downward
on the shaft until the stop collar is locked in place
Figure 4: Locking the Lock Collar
7. Purge and pressurize the pipeline according to company policy and standards.
8. Connect customer-supplied tubing from the sample outlet to the analyzer or pressure regulator.
1. Open the two isolation valves, A and B, on the liquid eliminator.
2. Check the system for leaks, especially between the pipeline connection and probe. Repair as
necessary.
3. Set the regulator on the analyzer, and purge the line to the analyzer according to company policy
and standards.
4. During operation, observe the ball in the ALS (Figure 5). If the ball rises to shut off the ALS,
indicating that liquid has entered the system, cease operation and perform maintenance on the
system.
Retracting the Probe:
1. Depressurize the pipeline to approximately 100 psi for safe retraction.
Ensure the pipeline is depressurized to below 110 psig for safe manual retraction.
Retracting the probe at a pipeline pressure greater than 110 psig may result in injury to the
operator or damage to the equipment.
2. Push downward on the unit, and simultaneously loosen the stop collar bolts.
IOM-164
PART #: LE2SSKO-MI with ALS
Rev: -
Last Updated: 1/15/2013
Page 6 of 11
3.
4.
5.
6.
Failure to maintain downward force on the probe unit while loosening the lock collar may
cause the probe to retract too quickly, possibly resulting in damage to the equipment or
injury of personnel.
Slowly allow pipeline pressure to push the probe shaft out of the pipeline. Gently pull up on the
probe shaft as needed until the probe is fully retracted.
Maintain downward pressure and allow the probe to retract slowly; do not allow the
shaft to bend. Do NOT retract the probe at pressures higher than the pressure specified
in Table 1 of these instructions.
Close the pipeline isolation valve.
Ensure the probe is fully retracted prior to closing the isolation valve. Failure to fully
retract the probe shaft prior to closing the isolation valve is the leading cause of damage to
Welker® probes.
Open the valve on the probe to relieve any remaining pressure from the probe.
Unbolt the unit from the flanged pipeline connection. The unit is now ready for maintenance or
to be moved to another location.
IOM-164
PART #: LE2SSKO-MI with ALS
Rev: -
Last Updated: 1/15/2013
Page 7 of 11
Section 3:
MAINTENANCE
1. Welker® recommends that the unit have biannual maintenance under normal operating
conditions. In cases of severe service, dirty conditions, excessive usage, or other unique
applications that may lead to excess wear on the unit, a more frequent maintenance schedule may
be appropriate.
2. Prior to maintenance or disassembly of the unit, it is advisable to have a repair kit available for
repairs of the system in case of unexpected wear or faulty seals.
3. All maintenance and cleaning of the unit should be done on a smooth, clean surface.
4. It is advisable to have the following tools available for maintenance of this unit. Tools needed
may vary depending on the product model.
Small pick, knife or other pointed instrument
1. Close the two isolation valves, A and B, on the liquid eliminator (Figure 1).
2. If maintenance is needed on the lower housing or probe shaft, refer to Section 2.4 to retract the
unit from the pipeline. Most routine maintenance can be performed without retracting the unit.
3. Remove all tubing and fittings connected to the system.
4. Unscrew the ALS from the hex nipple.
5. Unscrew the hex nipple from the liquid eliminator, and lift the ALS away from the liquid
eliminator.
ALS Maintenance (Figure 5):
1. Unscrew and remove the top cap of the ALS.
2. Remove the glass assembly. Polish gently with a clean, dry cloth as necessary.
3. Remove and replace all seals in the device.
4. Remove the ball. Examine the ball for scratches or wear. Replace as necessary.
5. Reinsert the ball into the guide.
6. Reinstall the glass assembly inside the cap.
7. Hand-tighten the cap to the body. Set the ALS aside.
Figure 5: ALS Maintenance Diagram
IOM-164
PART #: LE2SSKO-MI with ALS
Rev: -
Last Updated: 1/15/2013
Page 8 of 11
Liquid Eliminator Maintenance (Figure 6):
8. Unscrew the eight cap screws from the liquid eliminator top cap, and lift the top cap away to
expose the screen.
9. Remove the screen on the liquid eliminator.
10. Use a pick or small knife to remove the O-ring.
11. Remove the copolymer filter element.
12. Use solvent to clean the inside of the liquid eliminator. Do not leave any residue, which may
prevent the unit from functioning properly when the device is pressurized.
13. Center the copolymer filter inside the liquid eliminator.
14. Replace the O-ring.
15. Center the screen over the center of the element.
16. Set the liquid eliminator top cap on top of the screen.
17. Screw the eight cap screws into the liquid eliminator top cap in a crisscross bolting pattern. Set
the liquid eliminator aside.
Figure 6: Liquid Eliminator Maintenance Diagram
Adapter Maintenance (Figure 7):
1. Unscrew the liquid eliminator from the adapter.
2. Unscrew the two set screws in the adapter locking clamp.
3. Remove the adapter locking clamp from the bottom of the adapter. Be careful not to lose the
small adapter pin when separating the adapter and the adapter locking clamp.
4. Gently slide the probe shaft out of the adapter. The lock collar and lubricator body should stay
attached to the probe at this time.
5. Replace the O-ring in the adapter body. Set the adapter aside.
Figure 7: Adapter Maintenance Diagram
IOM-164
PART #: LE2SSKO-MI with ALS
Rev: -
Last Updated: 1/15/2013
Page 9 of 11
Lower Housing Maintenance (Figure 8):
1. Remove the lock collar set screws from the lock collar, and then remove the lock collar from the
probe shaft.
2. Inspect the probe shaft for scratches and polish or replace as necessary.
3. Gently slide the probe shaft out of the lubricator body.
4. As needed, replace the wiper ring at the top of the packing adjustment nut.
5. As needed, remove the packing adjustment nut and replace the packing, then screw the packing
adjustment nut back into the lubricator body.
6. Replace the O-ring in the lubricator body.
Figure 8: Lower Housing Maintenance Diagram
Reassembly:
7. Gently slide the probe shaft back through the lubricator body.
8. Attach the lock collar back onto the probe shaft, leaving it slightly loose.
9. Screw the adapter back onto the probe shaft.
10. Screw the liquid eliminator back onto the adapter.
11. Screw the hex nipple into the outlet port of the liquid eliminator.
12. Screw the ALS inlet onto the hex nipple.
13. Screw the adapter into the adapter port of the liquid eliminator.
14. Reconnect all necessary tubing and fittings. Refer to Section 2 for installation and operation
instructions.
1. If noticeable leaking occurs at the lower housing, tighten the adjustment packing nut (Figure 8).
2. The adjustment packing nut emergency shut-off is a temporary measure only. As soon as
possible, retract the unit from the pipeline and perform maintenance as needed on the lower
housing.
IOM-164
PART #: LE2SSKO-MI with ALS
Rev: -
Last Updated: 1/15/2013
Page 10 of 11
APPENDIX
Welker® Installation, Operation, and Maintenance Manuals suggested for use with this unit:
None
Other Installation, Operation, and Maintenance Manuals suggested for use with this unit:
None
Welker® drawings and schematics suggested for use with this unit:
Assembly Drawing: AD126EF
13839 West Bellfort
Sugar Land, TX 77498-1671
Phone: (281) 491-2331
Fax: (281) 491-8344
Toll Free: (800) 776-7267
Web Page: www.welkereng.com
IOM-164
PART #: LE2SSKO-MI with ALS
Rev: -
Last Updated: 1/15/2013
Page 11 of 11